Creating a new manufacturing facility for Danish Crown
Project overview
Conversion of a new spec built warehouse into a meat processing facility for a marketing leading global food supplier
NIRAS are responsible for designing the conversion of a c.9000m building into a high care food facility with the implementation carried out in-house with IFP Construction.
Challenge
Working with a pre-constructed building not designed for food manufacture and converting it via an internal fit-out, to ensure that it can meet BRC Standards within a challenging time frame.
Duration: 20 months
Total project value: £40 million
Construction Project value: £35 million 12 months
Project stage: implementation stage, completion Autumn 2023
NIRAS role: Building design
IFPC role: Principal Contractor